Full Year Statutory Accounts
Released
Released
Announcement PDF
Fulcrum Lithium Ltd
and its controlled entities
ABN: 23 665 528 307
Financial Statements
For the Financial Year Ended 30 June 2026
Fulcrum Lithium Ltd
and its controlled entities
For the Year Ended 30 June 2026
Contents
Page
Review of Operations 1
Corporate Governance Statement 27
Directors' Report 28
Lead Auditor's Independence Declaration 40
Consolidated Statement of Profit or Loss and Other Comprehensive Income 41
Consolidated Statement of Financial Position 42
Consolidated Statement of Changes in Equity 43
Consolidated Statement of Cash Flows 44
Notes to the Consolidated Financial Statements 45
Consolidated Entity Disclosure Statement 62
Directors' Declaration 63
Independent Auditor’s Report 64
Additional ASX Information 70
Corporate Directory 73
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
1
The Directors present their report together with the consolidated financial statements of the Group, comprising Fulcrum
Lithium Ltd (Fulcrum or the Company) and its controlled entities, for the year ended 30 June 2026.
REVIEW OF OPERATIONS
Fulcrum Lithium Ltd listed on the ASX on 22 November 2024, to explore a large lithium exploration lode claim holding area,
in the heart of Nevada’s ‘lithium belt’ which hosts Albemarle Corporation’s (NYSE: ALB) Silver Peak lithium mine, the only
lithium producing mine in the USA.
The Company’s two lithium projects in Nevada, USA are:
• the Alkali Flats lithium project comprising 802 lode claims (approximately 66 km2
);
• the Dry Canyon lithium project comprising 536 lode claims (approximately 45 km2
); and
The projects are targeting the Miocene aged lacustrine claystones, which host in excess of 100 million tonnes of reported
lithium carbonate equivalent resources at several deposits in nearby third-party projects in Nevada.
Figure 1. FULCRUM’S PROJECT LOCATIONS
During the year ended 30 June 2026, the Company completed 1 drilling program (Phase 3) at the Alkali Flats project and 2
geophysical surveys. Metallurgical studies and geological and resource modelling were also completed leading to the
maiden mineral resource estimate (MRE) which was subsequently announced on 4th
August 2026.
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
2
Alkali Flats Project
The Company owns a 100% interest in the Alkali Flats lithium project comprising 802 lode claims (approximately 66km2)
located within the Esmeralda County on Federal public lands owned and administered by the United States government.
The project is situated approximately 15km south of the Tonopah Flats (American Battery Technology Company) and TLC
(American Lithium Corporation) lithium projects and 10km east of the Silver Peak (Albemarle Corporation) lithium mine, the
only operating lithium mine in the USA (Figure 2).
Figure 2. FULCRUM’S ALKALI FLATS PROJECT LOCATION
Alkali Flats Geophysical Survey
As part of the appraisal program following the Alkali Flats Phase 2 drilling discovery of lithium mineralisation, Fulcrum
completed a 25km Controlled-Source Audio-Frequency Magnetotelluric (CSAMT) geophysical survey which has provided a
high-quality final dataset. The CSAMT survey was completed to map potential extensions of lithium claystones intersected
in the Phase 2 drilling and to optimise the drill hole locations in the upcoming Phase 3 drilling campaign.
CSAMT surveys are a commonly used geophysical technique for identifying the presence of highly electrically conductive
rocks, such as claystones, by transmitting harmless electrical signals into the ground and recording the response at receiver
stations, with high resolution at shallow depths. The 2D survey lines were designed in an EW parallel grid to tie into existing
Phase 2 drill holes for data and geological calibration and to map the basin architecture to guide the 3D geological and
resource models.
The 25km CSAMT geophysical survey was conducted between 1 October 2025 to 17 October 2025 with high quality data
reported during both field operations and final processing audits.
The 2D inversion sections (Figure 4) were interpreted by the Fulcrum geological team. High confidence extensions of lithium
mineralised claystones of the Seibert Formation were interpreted along with overburden gravel thickness, basement terranes
as well as structural trends and extensional faults. At AF2-2 drill hole location (Figure 5), where mineralisation remains open
at depth and currently 112m thick, the CSAMT data is detecting a potentially very thick lithium claystone interval over 300m
thick and importantly, structural dips and upthrown fault blocks are interpreted to bring thick mineralised clays much closer
to the surface, less than 25m. The mapped extensions and structural information were crucial for the planning of the Phase
3 drilling program and as input into the geological and resource models.
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
3
Figure 3. ALKALI FLATS CSAMT SURVEY LOCATION
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
4
Figure 4. ALKALI FLATS CSAMT 2D INVERSION RESULTS
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
5
Figure 5. CSAMT 2D INVERSION DATA WITH BASIC INTERPRETATION
(LINES L100 AND L300)
Figure 6. CSAMT SURVEY RECIEVER DEPLOYMENT AT THE ALKALI FLATS PROJECT
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
6
Alkali Flats Phase 3 Drilling Program
The Alkali Flats Phase 3 drill program commenced on 27th
January 2026 and was completed by 29th
March 2026. Completion
of the Phase 3 drill program marked an important milestone in the appraisal of the Alkali Flats lithium project following the
successful significant discovery following the success of Phase 2 drilling1
, geophysical surveying2
and initial metallurgy work4
completed to date.
The Phase 3 drilling program comprises 39 holes (Figure 7) totalling 5,787m, representing a 5-fold increase in the amount
of drilling over the deposit and reducing the hole spacing from a currently wide spacing averaging 2,000m down to 600m in
the core of the project which significantly increases the data density, reduces uncertainty and increases confidence in
modelling and resource estimations. The Alkali Flats Phase 3 drill program provided the increased drill hole density and
crucial information to enable Fulcrum’s maiden Mineral Resource Estimate following integration of all the geological,
geophysical and engineering data.
Table 1 is a list of all Phase 3 drill holes completed and their coordinates using NAD 83 Zone 11 datum.
Table 1. ALKALI FLATS PHASE 3 DRILL HOLE LOCATIONS AND DEPTH
Drill Hole ID Easting Northing
Elevation
(M)
Total Depth
(M)
AF3-E1 471980 4185032 1582 102
AF3-E2 474332 4183094 1655 102
AF3-E3 473872 4183470 1639 142
AF3-E4 473833 4182753 1656 87
AF3-E5 472953 4184241 1576 145
AF3-E6 473207 4182589 1673 47
AF3-E7 473307 4183270 1668 78
AF3-E8 472812 4183694 1634 47
AF3-E9 472476 4184628 1601 169
AF3-E10 471210 4184757 1591 125
AF3-E11 471624 4185733 1559 209
AF3-E12 472252 4185397 1571 261
AF3-E13 472696 4185158 1591 261
AF3-E14 473333 4184818 1603 197
AF3-E15 473529 4184337 1610 288
AF3-E16 473911 4184109 1628 136
AF3-E17 473915 4184553 1609 264
AF3-E18 474333 4183808 1633 183
AF3-E19 470750 4188796 1493 122
AF3-E20 470346 4187827 1502 148
AF3-E21 471253 4187052 1520 122
AF3-E22 471604 4187732 1510 148
AF3-E23 471657 4186273 1575 221
AF3-E24 471051 4186074 1739 122
AF3-E25 473535 4185404 1693 203
AF3-E26 473380 4186107 1741 244
AF3-W1 467736 4187642 1505 38
AF3-W2 466323 4187007 1476 73
AF3-W3 464844 4186776 1482 133
AF3-W4 463983 4187100 1472 111
AF3-W5 465813 4186047 1489 75
AF3-W6 464747 4185604 1479 139
AF3-W7 463536 4184808 1473 123
AF3-W8 464120 4183742 1475 183
AF3-C01 474329 4183099 1645 94
AF3-C02 472947 4184243 1603 140
AF3-C03 471629 4185732 1534 217
AF3-C04 464746 4185603 1499 152
AF3-C05 463982 4187106 1479 136
TOTAL 5,787
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
7
Figure 7. ALKALI FLATS PHASE 3 DRILL PROGRAM
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
8
The program was designed to infill drill the Phase 2 discovery as well as extend the discovery in open directions. Of the 39
holes, 34 intersected lithium mineralization greater than 300 ppm Li. The full table of significant lithium assay results can be
found in Table 2. The thickest zones intersected are highlighted as:
• AF3-E13: 147.9m @ 507ppm Li with internal values up to 1,145ppm Li
• AF3-E14: 112.8m @ 546ppm Li with internal values up to 903ppm Li
• AF3-E26: 103.7m @ 541ppm Li with internal values up to 965ppm Li
• AF3-E15: 94.5m @ 563ppm Li with internal values up to 1,070ppm Li
• AF3-W3: 91.5m @ 569ppm Li with internal values up to 1021ppm Li
• AF3-E9: 86.9m @ 500ppm Li with internal values up to 933ppm Li
• AF3-E5: 86.9m @ 587ppm Li with internal values up to 953ppm Li
• AF3-E25: 80.8m @ 572ppm Li with internal values up to 1,063ppm Li
Figure 8. RC DRILL RIG ONSITE AT ALKALI FLATS PHASE 3 PROGRAM
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
9
Figure 9. CORE OF SEIBERT FORMATION CLAYSTONE (AF3-CO2, 330ft - 440ft)
Table 2. PHASE 3 ASSAY RESULTS SHOWING ZONES ABOVE 300PPM Li
Drill Hole ID From (m) To (m) Interval(m) Li (ppm)
AF3-E1 35.1 79.3 44.2 530
AF3-E2 38.1 86.9 48.8 722
including 41.2 56.4 15.2 834
AF3-E3 82.3 128.0 45.7 713
including 93.0 102.1 9.1 898
AF3-E4 39.6 73.2 33.5 668
including 44.2 50.3 6.1 801
AF3-E5 44.2 131.1 86.9 587
including 80.8 93.0 12.2 802
AF3-E6 7.6 32.0 24.4 577
also 39.6 42.7 3.0 482
AF3-E7 44.2 61.0 16.8 546
AF3-E8 29.0 30.5 1.5 430
also 41.2 42.7 1.5 764
AF3-E9 64.0 150.9 86.9 500
including 114.3 117.4 3.0 845
AF3-E10 No mineralization >300 ppm Li
AF3-E11 70.1 163.1 93.0 433
also 170.7 172.3 1.5 419
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
10
Drill Hole ID From (m) To (m) Interval(m) Li (ppm)
AF3-W1 No mineralization >300 ppm Li
AF3-W3 25.9 117.4 91.5 569
including 38.1 41.2 3.0 833
AF3-W4 35.1 109.8 74.7 511
including 42.7 47.3 4.6 816
AF3-W5 7.6 35.1 27.4 520
also 56.4 59.5 3.0 521
AF3-W6 39.6 111.3 71.6 520
also 115.9 122.0 6.1 599
AF3-W7 No mineralization >300 ppm Li
AF3-E12 122.0 138.7 16.7 378
also 143.3 257.6 114.3 461
AF3-E13 112.8 260.7 147.9 507
including 198.2 221.0 22.8 838
AF3-E14 64.0 176.8 112.8 546
including 109.8 129.6 19.8 809
AF3-E15 59.5 154.0 94.5 563
including 97.6 111.3 13.7 806
AF3-E16 35.1 106.7 71.6 602
including 54.9 68.6 13.7 802
AF3-E17 57.9 117.4 59.5 696
including 71.6 96.0 24.4 841
AF3-E18 99.1 173.8 74.7 695
including 115.9 140.2 24.3 862
AF3-E19 67.1 93.0 25.9 491
also 99.1 108.2 9.1 420
also 125.0 129.6 4.6 664
AF3-E20 13.7 19.8 6.1 397
AF3-E21 57.9 67.1 9.2 547
also 73.2 105.2 32.0 482
AF3-E22 No mineralization >300 ppm Li
AF3-E23 108.2 150.9 42.7 387
also 157.0 167.7 10.7 413
also 172.3 184.5 12.2 433
also 210.4 221.0 10.6 312
AF3-E24 No mineralization >300 ppm Li
AF3-E25 76.2 157.0 80.8 572
including 126.5 146.3 19.8 903
also 164.6 190.5 25.9 589
AF3-E26 96.0 199.7 103.7 541
including 166.2 190.5 24.3 829
also 207.3 231.7 24.4 437
Drill Hole ID From (m) To (m) Interval(m) Li (ppm)
AF3-C01 (Twin of
AF3-E2)
39.0 85.1 46.1 712
including 42.9 54.8 11.9 827
AF3-C02 (Twin of
AF3-E5)
46.0 134.7 88.7 563
including 76.2 96.3 20.1 805
AF3-C03 (Twin of
AF3-E11)
71.8 94.0 22.2 386
also 97.6 156.3 58.7 432
AF3-C04 (Twin of
AF3-W6)
33.2 119.2 86.0 461
AF3-C05 (Twin of
AF3-W4)
25.6 108.7 83.1 464
AF3-W8 137.2 138.7 1.5 376
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
11
Figure 10. ALKALI FLATS PHASE 3 DRILL PROGRAM ASSAY RESULTS
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
12
Figure 11. ALKALI FLATS SCHEMATIC CROSS SECTION A-A’
The Phase 3 drilling data confirmed the large scale potential identified in Phase 2 discovery and geophysical survey data,
and exceeded expectations in several respects. The thickness of the mineralised zone in the core of the discovery, the large
lateral extent proven by step out holes and the highly correlatable and continuous nature of the mineralised zones over more
than 8km in strike, with the deposit remaining open in 3 of the 4 directions, demonstrated the large-scale potential of the
deposit. Phase 3 data was critical for incorporating into the geological model to demonstrate the full scale and high
confidence estimation of the deposit with the maiden resource estimate.
Alkali Flats Metallurgy Program
Following the Alkali Flats Phase 2 RC drilling program lithium claystone discovery, zones of up to 30 metres were selected
across 5 drill holes representing higher grade, lower grade zones and 2 control zones. Samples across each zone were
composited to represent the average properties over the broader 30m zone. Samples were run through the analytical
process by Kappes, Cassiday and Associates (KCA) in Reno, Nevada, in a workflow that included a head analysis of
mineralogy and lithium grade, particle size screening, sulfuric acid leaching tests with varying acid strengths and
temperature.
Results from the head screening analysis demonstrate that in the higher-grade zones, 97%-100% of the lithium was
contained in the <0.045mm particle size fraction and up to 42% of carbonate (calcite) was removed in the >0.045mm particle
size fraction.
Table 3. HEAD GRADE ANALYSIS LITHIUM GRADE
ZONE 1 ZONE 2 ZONE 3 ZONE 4
ZONE 5
(CONTROL) ZONE 6
ZONE 7
(CONTROL) ZONE 8
Hole AF2-2 AF2-2 AF2-3 AF2-4 AF2-4 AF2-5 AF2-5 AF2-10
Depth From (m) 100 183 134 16 82 53 133 52
Depth To (m) 130 213 147 34 112 83 136 82
Lithium (mg/kg) 414 652 472 636 156 674 142 592
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
13
Figure 12. 4 HOUR SULFURIC ACID LEACH RESULTS WITH VARYING ACID STRENGTHS
Figure 13. 4 HOUR SULFURIC ACID LEACH RESULTS WITH VARYING TEMPERATURES
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
14
Mineralogical analysis using Quantitative X-Ray Diffraction (QXRD) was completed to understand the mineral composition
of the lithium claystones as well as the clay-types present. Results from this analysis describe the claystones as a mixture
of illite and smectite clays containing calcite, K-feldspar and plagioclase fractions. This claystone composition is similar to
other lithium clay deposits of the Siebert Formation in the local Esmeralda County area.
Following the success of the first series of tests in the Company’s initial metallurgical further tests were conducted focused
on beneficiation and leaching techniques. The further metallurgical test work conducted by KCA included hydrocyclone
separation, alcohol screening and roast calcination followed by water leaching. These tests were designed to gain a further
understanding of the leachability of the Alkali Flats lithium bearing claystones, to compare the performance of different clay
zones within the project, to analogue other nearby claystone projects and to guide and accelerate a more detailed
metallurgical program from drill core from the current Phase 3 drilling program.
Alcohol Screening
The clay samples were wet screened using isopropyl alcohol with a 0.020mm size screen to separate the solids by particle
size. The undersized and oversized fractions were dried, weighed, and assayed to determine the degree of separation of
lithium bound in clay particles, carbonates, which are a major acid consumer, and the reduction in mass.
Hydrocyclone Separation
A laboratory scale hydrocyclone (25mm diameter) was used to separate the 5% solid clay slurry by density. The underflow
and overflow fractions were dried, weighed and assayed to determine the degree of separation of lithium bound in clay
particles, carbonates which are a major acid consumer and the reduction in mass.
Roast Calcination and Water Leach
Clay samples were pulverized and pelletized with varying blend ratios of gypsum, limestone using water. The pellets were
roasted at 1,000°C for 1 hour at atmospheric pressure. The pellets were water leached with agitation for 1 hour. The leachate
and the tailings were assayed to determine the percentage of lithium that was extracted from the clay pellets.
Mini-Column Tests
Clay samples were pelletized and sulfuric acid cured. 1kg of pellets was placed in a 75mm diameter column under a diluted
sulfuric acid drip for 7 days. The leachate and clay tailings were assayed to determine the percentage of lithium that was
extracted from the clay pellets. Measurements of the leachate solution were taken every 24 hours to track the progress of
clay material lithium extraction.
Table 4. BENEFICIATION AND LEACHING TESTS RESULTS SUMMARY
AF2-2 (Zone 2) AF2-5 (Zone 6) AF2-10 (Zone 8)
Mass Reduction 12% 15%
Carbonate Reduction 30% 10%
Grade Increase 12% 11%
AF2-2 (Zone 2) AF2-5 (Zone 6) AF2-10 (Zone 8)
Mass Reduction 26% 29% 41%
Carbonate Reduction 53% 54% 41%
Grade Increase 15% 13% 27%
AF2-2 (Zone 2) AF2-5 (Zone 6)
Lithium Extraction Roast Blend A Roast Blend B Roast Blend C
66% 59% and 57% 30% and 12%
AF2-2 (Zone 2) AF2-5 (Zone 6) AF2-10 (Zone 8)
Lithium Extraction 95% 96% 93%
Not Run Not Run
Not Run
Roast Calcination and Water Leach
7-Day Mini Column Leach
AF2-10 (Zone 8)
Alcohol Screening
Hydrocyclone Separation
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
15
Figure 14. 7 DAY MINI-COLUMN LEACH RESULTS
Alkali Flats Maiden Mineral Resource Estimation
Following the Alkali Flats Phase 3 appraisal drilling program completed in March 2026, the Company incorporated all drilling,
assay and geophysical data into a 3D geological and resource model. Fulcrum announced the maiden Mineral Resource
Estimate (MRE) subsequent to the reporting period, on 4th
August, 2026. The company achieved the project’s major
milestone with a large-scale lithium resource estimate delivered within 12 months from discovery.
The total resource defined by the maiden MRE of 10.7 Mt of contained Lithium Carbonate Equivalent (LCE), represents a
resource of globally significant scale and comparable in size to several advanced lithium claystone projects in Nevada,
including American Battery Technology’s Tonopah Flats project (18.7 Mt LCE)5
and American Lithium Corp’s TLC project
(10.0 Mt LCE)5
and currently is the 7th largest reported estimate of domestic lithium resources in the United States (Figure
19).
The high degree of geological spatial continuity of the Alkali Flats lithium deposit, assessed from the 44 drill hole penetrations,
combined with higher density drill spacing (approximately 600m) in the core of the deposit, have strongly supported a
significant proportion of the resource estimate to have a higher confidence resource classification (Figure 15). The total
measured and indicated resource of 4.3 Mt LCE represents 40% of the total resource.
Accompanying the large resource estimate, opportunities for future drilling to upgrade the resource, focusing on the
shallower, higher-grade domains of the resource which vector to the south-east of the deposit, provide clear targets for future
growth of higher confidence and higher value resources.
Following this project major milestone, work will continue to focus on identifying the lowest cost processing options through
the multi-pathway metallurgical test work program that is already underway, building off the positive results from the initial
metallurgical program which achieved lithium extractions up to 96%4
.
Table 5. Alkali Flats Maiden Mineral Resource Estimate at 400ppm Li cut-off grade
Resource Category Mass (Mt) Li (ppm) LCE (ppm) Contained Li (Mt) Contained LCE (Mt)
Measured 715 604 3,212 0.43 2.30
Indicated 677 564 3,003 0.38 2.03
Measured +
Indicated
1,392 585 3,114 0.81 4.33
Inferred 2,177 549 2,925 1.20 6.37
TOTAL 3,570 563 2,997 2.01 10.70
Lithium Carbonate Equivalent (LCE) = Li x 5.323
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
16
Figure 15. Alkali Flats Resource Classification and Drill Hole Locations
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
17
Figure 16. Alkali Flats 3D Geological Model (Oblique View Looking Southwest)
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
18
Table 6. Mineral Resource Sensitivity to Lithium Cutoff Grade (Note: Reported Cut-off =
400ppm Li)
Li Cutoff
(ppm)
Classification Tonnes
(Bt)
Li Grade (ppm) LCE Grade (ppm) Contained Li
(Mt)
Contained LCE (Mt)
300 Measured 0.973 538 2,862 0.523 2.78
Indicated 1.002 496 2,641 0.497 2.65
Inferred 3.191 487 2,590 1.553 8.27
Total 5.166 498 2,651 2.573 13.70
400 Measured 0.715 604 3,212 0.431 2.30
Indicated 0.677 564 3,003 0.382 2.03
Inferred 2.177 549 2,925 1.196 6.37
Total 3.568 563 2,997 2.009 10.70
500 Measured 0.531 659 3,508 0.350 1.86
Indicated 0.394 650 3,459 0.256 1.36
Inferred 1.406 607 3,233 0.854 4.55
Total 2.331 626 3,334 1.460 7.77
600 Measured 0.359 711 3,786 0.255 1.36
Indicated 0.250 709 3,774 0.177 0.94
Inferred 0.618 677 3,602 0.418 2.23
Total 1.227 693 3,691 0.850 4.53
700 Measured 0.171 778 4,143 0.133 0.71
Indicated 0.116 781 4,158 0.091 0.48
Inferred 0.177 768 4,086 0.136 0.72
Total 0.464 775 4,125 0.360 1.92
Figure 17. Mineral Resource as a Function of Lithium Cut-Off Grade (Reported Cut-off =
400ppm)
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
19
Fulcrum’s 100% owned Alkali Flats project large-scale lithium resource ranks highly in total resource size as both a US
domestic lithium resource (ranking 7th
), as well as a reported MRE by ASX listed lithium exploration companies (ranking 3rd
)
(Figure 18).
Figure 18. ASX-Listed Lithium Exploration Company’s Reported Resource Estimates5
in
Lithium Carbonate Equivalent (LCE)
Figure 19. USA Domestic Lithium Project Reported Resource Estimates5
in Lithium
Carbonate Equivalent (LCE)
Alkali Flats Claims
During the reporting period, Fulcrum has reshaped the Alkali Flats Project claims position to reflect drilling results and
resource estimation work completed. In August 2025, 512 claims were renewed for the 2025/2026 BLM lease maintenance
year. In October 2025, an additional 281 claims were staked and filed to increase the number of claims to 802. At the end
of the reporting period, Alkali Flats consisted of 802 claims.
After the reporting period, based on the Phase 3 drilling results and resource estimation work, the company has reshaped
the claims of the Alkali Flats project to relinquish areas that did not contain resource potential around the margins of the
claims boundary. After the reporting period, 657 claims were renewed for the 2026/2027 BLM lease maintenance year
providing a significant saving in annual claim maintenance costs.
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
20
Dry Canyon Project
In November 2025, Fulcrum filed 201 unpatented load claims in Lander County, Nevada, on Federal public land. The claims
were staked by the Company and, within 90 days of staking, filed with the USA Bureau of Land Management (BLM). The
load claims (Figure 20) give Fulcrum the right to access and conduct mineral exploration and mining under the guidelines
and rules set forth in General Mining Act of 1872, and include rights to all locatable surface minerals.
Basin geology includes the presence of an abundance of volcanic source rocks with 2 major calderas flanking the project as
well as a closed sedimentary and hydrologic basin, tuffaceous lacustrine sediments and basin and range extensional tectonic
subsidence.
Figure 20. DRY CANYON PROJECT LOCATION
Dry Canyon Exploration
Following a state-wide review of lithium claystone opportunities, Dry Canyon emerged as the highest potential target based
on the geological features of basins that support high grade lithium potential. To support the desktop review, a surface
sampling program with a total of 62 samples were collected for assaying in Fulcrum’s initial surface sampling program
completed in November 2025, with 31 samples returning assay results above 300ppm Li and 6 samples above 1,000ppm
Li, confirming this potential (Figure 21).
In April 2026 a 13km CSAMT survey was completed, acquiring high quality 2D data providing key structural trends and
potential lithology identification (Figure 23). CSAMT surveys are a commonly used geophysical technique for identifying the
presence of highly electrically conductive rocks, such as claystones, by transmitting harmless electrical signals into the
ground and recording the response at receiver stations. Data quality was assessed during the QC and processing of the
data and was determined to be a high quality dataset.
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
21
The 2D inversion sections were interpreted by the Fulcrum geological team. Extensions of the claystone unit containing the
high-grade (up to 1,219ppm Li) lithium mineralised claystones sampled at surface are interpreted to extend beyond 500m
at the thickest parts and more than 200m across the whole project area (Figure 25). Overburden thickness, basement depth
as well as structural trends and extensional faults were able to be interpreted, with generally thin (<25m) overburden across
the majority of the project area. These geophysical interpretations form the basis of the drilling targets being planned in the
upcoming maiden drill program which will test and calibrate the geophysical responses and provide the first drilling of these
targets in the basin.
The interpretation of this geophysical data provides the first look at the structure of the basin and potential lithologies that
can indicate the potential for deposit scale, trend vectors and optimal drilling targets.
Subsequent to the encouraging results from the CSAMT survey, Fulcrum staked an additional 335 unpatented lode claims
to expand the project to 536 lode claims (approximately 45km2
), securing the high potential basin acreage on Federal public
land (Figure 22).
Figure 21. DRY CANYON CSAMT SURVEY WITH SURFACE SAMPLE LITHIUM ASSAYS
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
22
Figure 22. DRY CANYON CLAIMS EXTENSION LOCATION
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
23
Figure 23. DRY CANYON CSAMT SURVEY 2D INVERSION RESULTS
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
24
Figure 24. CSAMT 2D INVERSION DATA WITH BASIC INTERPRETATION
Dry Canyon Claims
After the reporting period, In September 2026, 253 claims had been renewed for the 2026/2027 BLM lease maintenance
year and an additional 283 claims were staked and in the process of being filed.
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
25
References
1. ASX: FUL 24 September 2025, ‘Alkali Flats Project Update – Lithium Discovery’.
2. ASX: FUL 17 November 2025, ‘Geophysical Survey Results Expand Alkali Flats Lithium Claystone Target’
3. ASX: FUL 25 May 2026, “Thickest and Highest Grade Lithium at Alkali Flats”
4. ASX: FUL 19 May 2026, “Alkali Flats Metallurgy Update”
5. Mineral Resource Estimate References
a. ASX:JLL, Jindalee Lithium, McDermitt PFS, 19 November 2024
b. ASX:LKE, Lake Resources, Kachi Resource Update, 3 June 2025
c. ASX:EMH, European Metals Holdings, Cinovec DFS, 23 December 2025
d. ASX: AZL, Arizona Lithium, Prairie MRE, August 2023
e. ASX:PMT, Patriot Battery Metals, Shaakichiuwaanaan MRE, August 2024
f. ASX:VMS, Venari Minerals, Red Mountain MRE, February 2026
g. ASX:WC8, Wildcat Resources, Tabba Tabba MRE, November 2024
h. ASX:WR1, Winsome Resources, Adina MRE, May 2024
i. ASX:INF, Infinity Lithium, Annual Report 2025
j. ASX:ASN, Anson Resources, Paradox MRE Update, October 2023
k. ASX:PUR, Pursuit Minerals, Rio Sur Grande, 2026MRE Update
l. ASX:GL1, Global Lithium Resources, Manna MRE, June 2024
m. ASX:A11, Atlantic Lithium, Ewoyaa MRE, July 2024
n. ASX:GT1, Green Technology Metals, Root ASX Report, June 2023
o. ASX:ELV, Elvera Lithium, Carolina Lithium DFS, January 2022
p. ASX:GW1, Greenwing Resources, San Jorge MRE, January 2025
q. NYSE:LAC, Lithium Americas, Thacker Pass MRE Update, January 2025
r. TSX:NVLH, Nevada Lithium, Bonnie Claire MRE Update, September 2024
s. NASDAQ:ABAT, American Battery Technology, Tonopah Flats PFS, September 2025
t. TSX:NILI, Surge Battery Metals, Nevada North MRE, June 2026
u. Pheonix Lithium, East, https://www.phoenixlithium.com/project
v. ASX:CC9, Chariot Resources, Horizon MRE, December 2023
w. TSX:LI, American Lithium Corp, TLC MRE Upgrade, February 2025
x. TSX:NEV, Nevada Sunrise, Gemini MRE, March 2024
y. TSX:LCE, Century Lithium, Clayton Valley PFS, January 2026
z. ASX:NLP, Future Battery Metals, NLP MRE, April 2024
aa. TSX:NRM, Noram Lithium Corp, Zeus Technical Report, May 2024
bb. NYSE: SLI, Standard Lithium, Smackover Project DFS, September 2023
cc. Authium, Clayton Ridge 2020 MRE
dd. TSX:SRJ, Spearmint Resources, McGee MRE, June 2022
ee. ASX:INR, Ioneer, Rhyolite Ridge SEC S-K 1300 Technical Report, April 2026
ff. NYSE:ALB, Albermarle Corporation, Kings Mountain/Silve Peak SEC Form 10-K FY2023
gg. AIM:BHL, Bradda Head Lithium, Basin MRE, July 2024
Fulcrum Lithium Ltd
and its controlled entities
Review of Operations
For the Year Ended 30 June 2026
26
No material changes